Construction updates

Construction updates

October 22 Progress Updates:

  • Building exterior finished with exception of decorative metal panels and exterior doors.
  • Interior work:
    • First coat of paint in final colors is complete.
    • Tile, vinyl flooring and carpet installation complete (except for limited areas where casework installation is ongoing).
    • Ceiling installation is complete.
    • Casework (cabinets and counter tops) installation is ongoing.
  • Site work:
    • Curbs, sidewalks, parking lots, campus roadways, and heliport are complete.
    • Trees and shrubs planting to be complete by end of October.
  • Utility and road work:
    • Sewer construction installation along USH-10 ongoing and to be complete by early November.
    • Reconstruction of River Avenue ongoing and to be complete by early November.

August 27 Progress Updates:

  • Building is fully enclosed – with exterior finishes being installed and permanent exterior door installation ongoing.
  • Interior work:
    • Drywall and first coat of paint is complete.
    • Tile in showers and toilet rooms is complete.
    • Vinyl flooring and carpet installation is ongoing.
    • Ceiling installation is ongoing.
  • Site work:
    • Finish grading complete and base material is spread in parking areas and campus drives.
    • Concrete curbs, sidewalks, loading dock and heliport have been installed.
    • Trees and shrubs have been planted in parking islands.
    • Lights for parking areas and campus drives are installed.

 July 23 Progress Updates:

  • Building is fully enclosed – with windows and exterior finishes being installed.
  • Interior work is ongoing -with plumbing, electric and HVAC nearing completion.
  • Site work:
    • Finish grading and placement of base material for parking areas and campus drives is ongoing.
    • Concrete curbs and sidewalks will be installed the beginning of the last week of August.

June 15 Progress Updates:

  • Interior work such as plumbing, electric, studs, drywall, paint, tile, flooring and ceilings is ongoing.
  • Site work:
    • Entrance drive has been widened with base material applied.
    • Finish grading and placement of base material for parking areas and campus drives is ongoing.
  • We Energies natural gas line is complete.
  • Clark Electric Coop cable has been installed.

May 21 Progress Updates:

  • Site work has re-started, including:
    • Grading and placement of base material for the campus entrance drive
    • Installation of concrete bases for light poles
    • Finish grading and placement of base material for parking areas and campus drives

May 15 Progress Updates:

  • Building is now fully enclosed
    • Windows are being installed and exterior finish installation is ongoing.
  • Interior work such as plumbing, electric, studs, drywall and flooring is ongoing
  • WE Energies continues gas line work.
    • Directional bore under Black River is complete.
    • Trenching along HWY 10 is ongoing.

May 8 Progress Updates:

  • Work on outside sealing, insulation, stucco, and metal are being done.
  • Brick work will be starting soon.
  • Roof is complete – all but two HVAC units are on the roof.
  • WE Energies are on HWY 10 boring the gas line under the river and to the site.
  • Water setup for building is complete.

April 23 Progress Updates:

  • Full building enclosed
    • Exterior insulation board to be covered by exterior finish system – installation to begin week of April 27
    •  Windows being installed to replace temporary plastic coverings
  • Roof for entire building complete
  • Interior build-out ongoing
  • Water line around building to be complete the week of April 27 providing access to city water
  • WE Energies to begin gas line work the week May 4 (8 week process)
    • Directional bore under the Black River
    • Trenching along HWY-10

 

View photos of progress below: